Work of the contract is for the replacement of the water mains and services,gravity sewer mains and services, installation of new storm sewersystem withmanholes and inlets, addition of curb ramps, replacement and extension ofconcrete sidewalks, replacement of driveways, removal of cross street boxdrainage, mill and asphalt overlay 49thStreet, refurbish signage and addpavement markings. Existing 8-inch and 6-inch water mains and 8-inchgravitysanitary sewer mains are to be abandoned in place once the new waterand sewer mains and water and sewer services are installed and operational.Conflict manholes are required. The Contractor will need to coordinate withthe underground utility providers for gas, cable, phone, and fiber optic.